Excerpts from the Federal Register, July 1, 2015
Summary
On January 27, 2010, the U.S. Nuclear Regulatory Commission (NRC) notified the public of its opportunity to participate in the scoping process associated with the preparation of an environmental impact statement (EIS) related to the review of the license renewal application submitted by Pacific Gas and Electric Company (PG&E) for the renewal of Facility Operating Licenses DPR-80 and DPR-82 for an additional 20 years of operation at Diablo Canyon Power Plant (DCPP), Units 1 and 2. The current operating licenses for DCPP, Units 1 and 2 expire on November 2, 2024, and August 26, 2025, respectively. The scoping period closed on April 12, 2010. The NRC has decided to reopen the scoping process and allow members of the public an additional opportunity to participate.
DATES:
The comment period for the environmental scoping process published on January 27, 2010 (75 FR 4427) has been reopened. Comments should be filed no later than August 31, 2015.
II. Discussion
…
On December 22, 2014 (ADAMS Package No. ML14364A259), and February 25, 2015 (ADAMS Package No. ML15057A102), PG&E amended its ER to provide additional information identified by NRC staff as necessary to complete the review of the DCPP license renewal application. By letter dated April 28, 2015 (ADAMS Accession No. ML15104A509), the NRC staff issued a schedule for the remainder of the DCPP license renewal review. The purpose of this notice is to (1) inform the public that the NRC has decided to reopen the scoping process, as defined in 10 CFR 51.29, “Scoping-environmental impact statement and supplement to environmental impact statement,” and (2) allow members of the public an additional opportunity to participate. The comments already received by the NRC will be considered; reopening of the scoping process provides additional opportunity for the public to comment on issues that may have emerged since completion of the last scoping period.
…
The NRC will first conduct a scoping process for the supplement to the GEIS and, as soon as practicable thereafter, will prepare a draft supplement to the GEIS for public comment. Participation in the scoping process by members of the public and local, State, Tribal, and Federal government agencies is encouraged. The scoping process for the supplement to the GEIS will be used to accomplish the following:
a. Define the proposed action, which is to be the subject of the supplement to the GEIS;
b. Determine the scope of the supplement to the GEIS and identify the significant issues to be analyzed in depth;
c. Identify and eliminate from detailed study those issues that are peripheral or that are not significant;
d. Identify any environmental assessments and other ElSs that are being or will be prepared that are related to, but are not part of, the scope of the supplement to the GEIS being considered;
e. Identify other environmental review and consultation requirements related to the proposed action;
f. Indicate the relationship between the timing of the preparation of the environmental analyses and the Commission’s tentative planning and decision-making schedule;
g. Identify any cooperating agencies and, as appropriate, allocate assignments for preparation and schedules for completing the supplement to the GEIS to the NRC and any cooperating agencies; andShow citation box
h. Describe how the supplement to the GEIS will be prepared and include any contractor assistance to be used.
III. Public Scoping Meeting
…
The NRC has decided to hold public meetings for the DCPP license renewal supplement to the GEIS. The scoping meetings will be held on August 5, 2015, and there will be two sessions to accommodate interested persons. The first session will convene at 1:30 p.m. and will continue until 4:30 p.m., as necessary. The second session will convene at 7:00 p.m. with a repeat of the overview portions of the meeting and will continue until 10:00 p.m., as necessary. Both sessions will be held at the Courtyard by Marriott San Luis Obispo, 1605 Calle Joaquin Road, San Luis Obispo, CA 93405. Both meetings will be transcribed and will include: (1) An overview by the NRC staff of the NEPA environmental review process, the proposed scope of the supplement to the GEIS, and the proposed review schedule; and (2) the opportunity for interested government agencies, organizations, and individuals to submit comments or suggestions on the environmental issues or the proposed scope of the supplement to the GEIS. Additionally, the NRC staff will host informal discussions one hour prior to the start of each session at the same location. Written comments on the proposed scope of the supplement to the GEIS will be accepted during the informal discussions. To be considered, comments must be provided either at the transcribed public meetings or in writing, as discussed above.
Persons may register to attend or present oral comments at the meetings on the scope of the NEPA review by contacting the NRC Project Manager, Michael Wentzel, by telephone at 1-800-368-5642, extension 6459, or by email at Michael.Wentzel@nrc.gov, no later than July 31, 2015. Members of the public may also register to speak at the meeting within 15 minutes of the start of each session. Individual oral comments may be limited by the time available, depending on the number of persons who register. Members of the public who have not registered may also have an opportunity to speak if time permits. Public comments will be considered in the scoping process for the supplement to the GEIS. Michael Wentzel will need to be contacted no later than July 22, 2015, if special equipment or accommodations are needed to attend or present information at the public meeting so that the NRC staff can determine whether the request can be accommodated.
More information and links to documents at
https://www.federalregister.gov/articles/2015/07/01/2015-15921/diablo-canyon-power-plant-units-1-and-2